Question

A can do a piece of work in 10 days; B in 18 days; and A, B and C together in 4 days. In what time would C alone do it?

Open in App
Solution

A can do a piece of work in = 10 days
B can do a piece of work in = 18 days
(A+B+C) can do a piece of work in = 4 days
A's 1 day work =110
B's 1 day work =118
(A + B)'s 1 day work =110+118=9+590
=1490=745
(A+B+C)'s 1 day work =14
C's 1 day work =14745
=4528180=17180
C can do the piece of work in =18017 days
=101017 days.


flag