wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A can do a piece of work in 11 days. B is 60% more productive than A. The number of days B will take to do the piece of work is:


A

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B

8 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
C

9 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
D

20 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
Join BYJU'S Learning Program