A can do a piece of work in 12 days. B can do this work in 16 days. A started the work alone. After how many days should B join him, so that the work is finished in 9 days?
A
5
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
4
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
3
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
2
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is A5 A′s work in 9 days =912=34
Remaining work =14
Remaining work was done by B in =14×16=4 days. ∴B should join A after 9−4=5 days.