The correct option is C 1015
B′s 3 days work =(121×3)=17
Remaining work =(1−17)=67
(A+B)′s 1 day work =(114+121)
=542
Now, 542 work is done by A and B in 1 day.
∴ 67 work is done by A and B in
(425×67)=365 days
Hence, total time taken =(3+365)=1015 days