Question

'A' can do a piece of work in 14 days while 'B' can do it in 14 days. They begin together. But, 3 days before the completion of work, 'A' leaves off.
Find the total number of days taken to complete the work.

Open in App
Solution

We will solve this using the LCM technique.

A takes 14 Days & B takes 21 Days. So, let the total work be LCM(14,21) = 42 Units

A -> 14 days = 3 Units/day
B -> 21 days = 2 Units/day
A + B = 5 Units/day

Now, for the last 3 days , only B worked as A left.

So, work done in the last three days = 2×3= 6 units

Work done by A & B together = 42–6 = 36 units

Time taken = 36/5 = 7.2 days

Thus, TOTAL TIME = 3+7.2 = 10.2 Days