CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

'A' can do a piece of work in 14 days while 'B' can do it in 14 days. They begin together. But, 3 days before the completion of work, 'A' leaves off.
Find the total number of days taken to complete the work.

Open in App
Solution

We will solve this using the LCM technique.

A takes 14 Days & B takes 21 Days. So, let the total work be LCM(14,21) = 42 Units

A -> 14 days = 3 Units/day
B -> 21 days = 2 Units/day
A + B = 5 Units/day

Now, for the last 3 days , only B worked as A left.

So, work done in the last three days = 2×3= 6 units

Work done by A & B together = 42–6 = 36 units

Time taken = 36/5 = 7.2 days

Thus, TOTAL TIME = 3+7.2 = 10.2 Days

flag
Suggest Corrections
thumbs-up
2
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Transposing Method
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon