CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A can do a piece of work in 20 days and B in 40 days. A begins the work and there after they work alternately one on each day. On which day will the work be completed?

A
24th day
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
25th day
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
26th day
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
27th day
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 27th day
Work done by (A+B) in 2 days =(120+140)=340
340 of the work is done by (A+B) in 2 days
Whole work is done by (A+B) in 2×403 days =803 days =2623 days
Work will be completed on 27th day.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon