A can do a piece of work in 20 days B in 15 days and C in 12 days. How soon can the work be done if A is assisted by B on one day and by C on the next alternately?
A
14 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
6 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
8 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
10 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is C8 days (A+B)′s1day work =(120+115) of the work, i.e., 760 (A+C)s1days work =(120+112), i.e. 860 of the work. 2 days work done =760+860=14. Since 14 of work is done in 2 days, so whole of the work is done in 8 days.