A can do a piece of work in 80 days. He works at it for 10 days and then B alone finishes the work in 42 days. The two together could have completed the work in _________.
A
24days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
25days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
30days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
35days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B30days Let total work =1
A's one day work =1/80
Let B take x days to finish work alone,
then B's one day work =1/x
Total Work done by A= (days worked by A)*(A's one day work)=10*(1/80)=1/8
Work left =1−1/8=7/8
Now B completes the left work in 42 days,
(B's one day work)×42=(7/8)
(1/x)×42=7/8
7x=8×42
x=48
(A+B)'s one day work =(1/80)+(1/48)
Total time needed by (A+B) to complete work =1180+148=30