wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A can do a piece of work in 9 days working 8 hours per day and B can do it in 6 days working 9 hours per day. If they will work together for 9 hours a day, then they will complete the work in

A
5 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
7 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
723days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
337 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 337 days
A can complete the whole work in =9×8=72 hours
A's 1 hour work =172
B can complete the whole work in =6×9=54 hours
B's 1 hour work =154
(A+B)’s 1 hour work =172+154=3+4216=7216
Both will finish the work in =2167 hours
Number of days required to finish the whole work, working together for 9 hours =2167×19=247=337 days
Option (c) is correct.

flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Ratio and Proportion
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon