A can do a work in 15 days and B in 20 days. If they work on it together for 4 days then the fraction of the work that is left is:
A’s 1 day’s work = 115
B’s 1 day’s work = 120
(A+B)’s 1 day’s work = (115+120)=760
(A+B)’s 4 days’ work = (760×4)=715
∴ Remaining work = (1−715)=815