A can do a work in 15 days and B in 20 days. If they together work on it for 4 days; what fraction of the work will be left?
A's 1 day work =115
B's 1 day work =120
(A + B)'s 1 day work =115+120
=4+360=760
(A + B)'s 4 days work =760×4=715
Remaining work =1−715=15−715
=815