A can finish a work in 18 days and B can do the same work in half the time taken by A. Then working together what part of the same work can they finish in a day?
A
16
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
19
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
25
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
27
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B16 A can finish a work in 18 days. B can finish a work in 9 days. So In one day A can finish 118 work.
and In one day B can finish 19 work. So, working together the work can they finish in a day. W=118+19=318=16 Answer is (A) ,16.