A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:
10 days
(B+C)’s 1 day’s work =(19+112)=736
Work done by B and C in 3 days =(736×3)=712
Remaining work = (1−712)=512
Now, 124 work is done by A in 1 day
So, 512 work is done by A in (24×512)=10 days