Question

A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:


A

6 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
B

10 days

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C

13 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
D

16 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B

10 days


(B+C)’s 1 day’s work =(19+112)=736

Work done by B and C in 3 days =(736×3)=712

Remaining work = (1712)=512

Now, 124 work is done by A in 1 day

So, 512 work is done by A in (24×512)=10 days


flag
Suggest Corrections
thumbs-up
3
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Introduction to Inverse Proportions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon