A can laid railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. How many days will C complete the work alone?
1 day’s work of (A + B + C) = 14
A’s 1 day’s work = 116
B’s 1 day’s work = 112
So, C’s 1 day’s work =14−(16+112)
=(14−778)=548
C alone can do the work in 485 days.