A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:
A
915 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
925 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
935 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
10
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is C935 days (A+B+C)'s 1 day's work =14 A's 1 day's work =116; B's 1 day's work =112; ∴C's 1 day's work =14−(116+112)=(14−748)=548 So, C alone can do the work in 485=935 days