A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:
(A + B + C)'s 1 day's work =14 |
A's 1 day's work =116 | ||
B's 1 day's work =112 | ||
C's 1 day's work = |
So, C alone can do the work in |