Question

A certain number of men can do a work in 60 days. If there were 8 more men, it could be completed in 10 days less. How many men were there in the beginning?

Open in App
Solution

Le the number of men at the beginning be x who completed the work in 60 days.
If 8 more men to joined to complete the same work
New number of men=x+8
No of days=6010=50days
60×x=50(x+8) Formula :If M1 men can complete a work in D1 days and M2 men can complete a work in D2 then =M1D1=M2D2
6x=5(x+8)
6x=5x+40
6x5x=40
x=40