A certain number of workers can finish a piece of work in 70 days. If there are 20 men less, it would take 10 more days for the same work to be finished. How many workers were there in the starting ?
A
140 workers
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
160 workers
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
152 workers
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
150 workers
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B 160 workers Let the number of workers in the starting be x.
Total work done will always be constant
Hence ⟹ No. of workers × work days = constant
⟹ x × 70 = (x - 20) × 80
⟹ 10x = 20 × 80
⟹ x = 20×8010 = 160
The number of workers in the starting is 160 workers