A certain piece of work can be completed by 108 men in 30 days.After 5 days , 8 men leave the job but 35 more men are employed.How much longer will the job take to be completed?
Open in App
Solution
But in 5 days, 108 men would have already completed (530)=(16)th of the work. So, remaining work is (56). Time needed by 135 men to finish (56)th of the work =(56)×24=20days