Question

A component can be produced by any of the four processes I, II, III and IV. The fixed cost and the variable cost for each of the processes are listed below. The most economical process for producing a batch of 100 pieces is

Process Fixed cost (in Rs.) Variable cost per piece (in Rs.)
I 20 3
II 50 1
III 40 2
IV 10 4

A
II
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
I
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
IV
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
III
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A II
Process Fixed cost (in Rs.) Variable cost per piece (in Rs.) Total cost (Rs.)
I 20 3 20 + 3 × 100 = 320
II 50 1 50 + 1 × 100 = 150
III 40 2 40 + 2 × 100 = 240
IV 10 4 10 + 4 × 100 = 410


Total cost is minimum for process II, hence process II is most economical.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
The Cost Curve
ECONOMICS
Watch in App
Join BYJU'S Learning Program
CrossIcon