A concrete pour of 1080 cum is planned with a 120 cum/hr capacity. If the effeciency of the plant is assumed to 75%, what will be approximate time taken for completing the pour?

A
8
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
9
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
12
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
7.5
No worries! We‘ve got your back. Try BYJU‘S free classes today!