Question

A contact on a construction job specifies a penalty for delay of completion beyond a certain date as follows, Rs. 200 for the first day, Rs. 300 for the second day, Rs. 400 for the third and so on if the total payment is Rs.2000 How many days did the contract has been delayed if no net money is transferred?

Open in App
Solution

There is no net money transferred so
penalty=Income
The penalty forms an AP with a=200;d=300200=100
Let the work be delayed for n days
So the total penalty is n2[2(200)+(n1)100]2000=n2[400+100n100]4000=100n(3+n)n2+3n=40n2+3n40=0n2+8n5n40=0n(n+8)5(n+8)=0(n+8)(n5)=0n=8,5
So the no.of days =5

flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Arithmetic Progression - Sum of n Terms
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon