wiz-icon
MyQuestionIcon
MyQuestionIcon
18
You visited us 18 times! Enjoying our articles? Unlock Full Access!
Question

A contract on construction job specifies a penalty for delay in completion of the work beyond acertain date is as follows: Rs. 200 for the first day, Rs.250 for the second day, Rs. 300 for the third day etc., the penalty for each succeeding day being 50 more than that of the preceding day. How much penalty should the contractor pay if he delays the work by 10 days?

A
Rs. 4950
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
Rs. 4250
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
Rs. 3600
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
Rs. 650
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B Rs. 4250
The penalty for delay on first day is 200, for second day is 250, for third day is 300 and so on.
The penalties form an arithmetic progression (AP) with a common difference of 50 and first element
as 200.

The sum of penalties for 10 days is thus same as the sum of numbers in the A.P. with n as 10.
Sum of AP (formula) =n2[2a+(n1)d]=102[2×200+(101)×50]=4250.

flag
Suggest Corrections
thumbs-up
11
similar_icon
Similar questions
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Fear of the Dark
QUANTITATIVE APTITUDE
Watch in App
Join BYJU'S Learning Program
CrossIcon