wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs. 200 for the first day, Rs. 250 for the second day, Rs. 300 for the third day, etc., the penalty for each succeeding day being Rs. 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days.

Open in App
Solution

It can be observed that these penalties are in an A.P. having first term as 200 and common difference as 50.

a = 200

d = 50

Penalty that has to be paid if he has delayed the work by 30 days = S30

= 15 [400 + 1450]

= 15 (1850)

= 27750

Therefore, the contractor has to pay Rs 27750 as penalty.


flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Per Capita Income, National Income and GDP
GEOGRAPHY
Watch in App
Join BYJU'S Learning Program
CrossIcon