Question

A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs. 200 for the first day, Rs. 250 for the second day, Rs. 300 for the third day etc., the penalty for each succeeding day being Rs. 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days?

Open in App
Solution

The money the contractor has to pay as a penalty forms an A.P.

We know,

Sn=n2[2a+(n1)d] ............ (Sum of n terms)

a= First term
d= Common difference
n= number of terms

Here,
a=200,d=50 and n=30

S30=302(400+50×29)=27750

flag
Suggest Corrections
thumbs-up
1
similar_icon
Similar questions
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Arithmetic Progression
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon