Question

A contractor estimated that 5 men would require 14 days to repair a house. How long will it take for 7 men to repair the same house?


A

19.6 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
B

10 days

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C

15 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
D

12 days

No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B

10 days


If the number of workers is increased, it would take less number of days to finish off the same task.

y : 14 : : 5 : 7

Hence it would take 10 days to repair the house.


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Inverse Proportions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon