A contractor estimates that 3 persons could rewire Jasminders house in 4 days. If he uses 4 persons instead of three, how long should they take to complete the job?

A
8 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
3 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
4 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
9 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!