A contractor undertook to build a road in 200 days. He employed 140 men. After 60 days, he found that only one-fourth of the road could be built. How many additional men should he employ to complete the work in time?
The correct option is A. 40
Amount of work remaining =1−14=34 units of work
Now, no. of days in which the remaining work needs to be completed =200−140=60 days
Let there be extra x men required to finish the work on time.
Now, efficiency of each of men
Since, efficiency of each men will remain same, therefore,
No. of men initially hired×No. of days they workedAmount of work completed=No. of men now required×No of days Work that is pending
⇒140×6014=(140+x)×14034
⇒3×60=140+x
⇒x=40