CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A contractor undertook to build a road in 200 days. He employed 140 men. After 60 days, he found that only one-fourth of the road could be built. How many additional men should he employ to complete the work in time?

A
40
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
60
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
80
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
None of these
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A. 40

Amount of work remaining =114=34 units of work

Now, no. of days in which the remaining work needs to be completed =200140=60 days

Let there be extra x men required to finish the work on time.

Now, efficiency of each of men

Since, efficiency of each men will remain same, therefore,

No. of men initially hired×No. of days they workedAmount of work completed=No. of men now required×No of days Work that is pending

140×6014=(140+x)×14034

3×60=140+x

x=40


flag
Suggest Corrections
thumbs-up
28
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Introduction to Direct Proportions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon