wiz-icon
MyQuestionIcon
MyQuestionIcon
11
You visited us 11 times! Enjoying our articles? Unlock Full Access!
Question

A department head has four tasks to be performed and there are only three subordinates. The estimation of the time (in hours) each subordinate would take to perform is given below in table.
Tasks/MenABCP92414Q17298R372218S143222The tasks are allocated to each man in such a way such that total time is minimized. What will be the minimum time?

A
34 hours
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
31 hours
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
35 hours
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
39 hours
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 39 hours
It is an unbalanced problem. For solving the problem we add a dummy subordinate.

Tasks/MenABCD(Dummy)P924140Q172980R3722180S1432220

Subtracting the smallest element of each column from all the elements of that column.

The optimum assignment is,
PA, QC, RB and S for a dummy man

Minimum time = 9 + 8 + 22 = 39 hours

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Central Tendency
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon