Question

A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?

A
23 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
37 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
3712
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
40 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is D 3712
Whole work is done by A in (20×54)=25 days.
Now, (1415) i.e., 15 work is done by A and B in 3 days.
Whole work will be done by A and B in (3×5) =15 days.
A's 1 day's work =125, (A+B)'s 1 day's work =115.
B's 1 day's work =(115325)=4150=275
So, B alone would do the work in 752=3712 days.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon