A does a work in 10 days and B does the same work in 15 days. In how many days will they together finish the same work?
6 days
A’s 1 day’s work = 110 and B’s 1 day’s work = 115
∴ (A+B)’s 1 day’s work = (110 + 115) = 16
So, both together will finish the work in 6 days.