Question

A does 45 of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?

A
23 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
37 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
3712 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
40 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 3712 days
A does 45 work in 20 day In 1 day A does 125 units of work
A and B do 15 work in 3 days In 1 day A and B do 115 units of work
Say B does 1x units of work in 1 day.
125+1x=115
1x=115125=1015×25
x=15×2510=37.5
B does the complete work in x days =37.5 days
Answer : Option D.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Arithmetic Progression - Sum of n Terms
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon