Question

A does 45th of work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work ?

A
23 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
37 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
3712 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
40 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 3712 days
Letthetotalworkbex.
ThespeedatwhichamountofworkAdoesin20daysis=x25
LetthespeedofBbeBworkperday.
Since,theworkdonebyAis45x
Remainingworkisx45x=x5
IfAandBworktogetherthenwehave,
x5x25+B=3
speedofB=2x75workperday.
IfBaloneworksthentheworkwillbecompletedinx2x75=3712days.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Unitary Method
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon