A does half as much work as B and C does half as much work as A and B together in the same time. If C alone can do the work in 40 days, all of them together will finish the work in
A
13 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
15 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
20 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
13.33 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution
The correct option is C13.33 days Letthetotalworkbexunits. ∴speedofCis=x40workperday. ∴SpeedofB=x30worksperday. ∴SpeedofA=x60worksperday. ∴SpeedofA+B+C=3x40worksperday. Ifallofthemworktogetherthentheywillfinishxworksinx3x40=13.33days.