A group of workers estimate to finish a work in 10 days, but 5 workers could not join the work. If the rest of them finished the work in 12 days, then the number of workers present in the team originally is
A
50
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
45
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
35
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
30
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution
The correct option is D
30 If 'W' is the original number of workers estimated to finish the work.