A hydroelectric power station take sits water from a lake whose water level is at a height of 50 m above the turbine. Assuming an overall efficiency of 40%, calculate the mass of water which must flow through the turbine each second to produce a power output of 1 MW.(Take g=10 ms−2).
Since effieciency is 40 %
Useful energy = 40% mgh
=40100×m×10×50
1MW = 200m
1000000 = 200m
m = 1000000200= 5000kg