A is three times more efficient worker than B and is therefore able to complete a work in 60 days less than B. What is the number of days that A and B together will take to complete the work?
A
22.5 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
22 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
24.5 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
24 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is C22.5 days
Let A complete the work in x days. Then, B will complete the same work in 3x days.
Given:-
3x−x=60⇒x=30 days
∴A will complete the work in 30 days.
⇒B will complete the work in 3×30=90 days.
(A+B)′s 1 day work =130+190=490
⇒(A+B) will complete the work in 904 days =22.5 days