A is thrice as efficient as B and B is twice as efficient as C. If A, B and C work together, how long will they take to complete a job which B completes in 10 days?
A
209 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
119 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
3 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
None of these
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is A209 days
Let the time taken by A = x days
∴ work done by A in 1 day = 1x
A is thrice as efficient as B.
⇒ time taken by B =3× time taken by A = 3x days
⇒ work done by B in 1 day = 13x
B is twice as efficient as C.
⇒ work done by C in 1 day = 16x
⇒ time taken by C =2× time taken by B =2×3x=6x days
According to the question-
B completes the job in 10 days
3x=10
⇒x=103
Work done of 1 day if A, B and C work together-
1x+13x+16x=310+330+360=18+6+360=2760=920
Hence, time taken to complete the job if A, B and C work together =209 days