A layer of clay of 8 m thickness is located between two sand layers. The coefficient of consolidation of the clay is 5×10−4cm2/sec . The fill material was placed over a very large area above the top sand layer . After 3 years, the percentage of additional pressure due to fill material will be carried by the soil grains at the middle of clay layer