A load of 100 kg is pulled up by 5 m. Calculate the work done. Take g=9.8 ms−2
5000 J
4900 J
4800 J
4700 J
Given, the mass of the object m=100 kg, height h=5 m and g=9.8 ms−2.
We know work done W=mgh
So, W=100×9.8×5=4900 J