wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A machine P can print one laakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours .All the machines are started at 9 a. m While machine P is closed at 11 a. m and the remaining two machines complete the work . Approximately at what time will the work be finished ?

A
11 : 30 a.m
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
12 noon
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
12 : 30 p.m
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
1 p.m
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 1 p.m
(P + Q + R)'s 1 hours' work = (18+110+112)=37120
Work done by (P + Q + R) in 2 hours = 2 ×37120=3760
Remaining work = (13760)=2360 (Q + R)'s 1 hours' work = (110+112)=1160
1160 of the work is done by (Q + R) in 1 hour 2360 of the work will bw done by (Q + R)
in 2360÷1160=2311=2111 hours 2 hours So the work will be finished
approximately 2 hours after 11 a.m., i.e, around 1 p.m

flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Validity of Statements
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon