CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 A.M. while machine P is closed at 11 A.M. and the remaining two machines complete work. Approximately at what time will the work (to print one lakh books) be finished?

A
11:30 A.M.
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
12 noon
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
12:30 P.M.
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
1:00 P/M/
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 1:00 P/M/
(P+Q+R)'s 1 hour's work =(18+110+112)=37120
Work done by P.Q and R in 2 hours =(37120×2)=3760
(Q+R)'s 1 hour's work=(110+112)=1160.
Now, 1160 work done is done by Q and R in 1 hour.
So, 2360 work will be done by Q and R in (6011×2360)=2311 hours 2 hours.
So, the work will be finished approximately 2 hours after 11 A.M i.e, around 1 P.M.

flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon