A man can do a piece of work in 5 days. He and his son working together can finish it in 3 days. In how many days can the son do it alone?
A
61/2 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
7 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
71/2 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
8 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is C71/2 days We know that , Number of days man required to do piece of work =5 days Number of days his son required to do piece of work =3 days
Let us consider number of days both man and his son require =x days
∴ We can calculate work done by man in 1 hour =1/5 Work done by his son in 1 hour =1/x Now, work done by both man and his son together in a 1 hour =1/3
Also the work done by both man and his son together in 1 hour is equal to the sum of the work done by each of them in 1 hour =1/5+1/x=(x+5)/5x