A man can finish a work in 12 days while B can finish the same work in 15 days. If both work together, then calculate the time taken to complete the work.
A can finish the work in 12 days.
He can finish 100% of the work in 12 days.
In 1 day he can finish (10012)%=8.33% of the work.
Similarly B can finish (10015)%=6.67% of the work in 1 day.
When they both work together, they can finish (8.33+6.67)%=15% of the work in 1 day
So, to complete 100% of the work, they will take (10015)e=6(23) days. Hence option (a).
2nd method:- Total work (W) = 12A = 15B , B=45A
n(A+B) = W = 12A or 15B (Here, we take 12A).