A mould cavity of 1200
cm3 volume has to be filled through a sprue of 10 cm length feeding a horizontal runner. Cross-sectional area at the base of the sprue is 2
cm2. The acceleration due to gravity is 9.81
m/s2.
Neglecting frictional losses due to molten metal flow, the time taken to fill the mould cavity is seconds (rounded off to 2 decimal places).
- 4.28