A mould having dimensions 100 mm × 90 mm × 20 mm is filled with molten metal through a gate with height h and C.S. are A, the mould filling time is t1. The height is now quadrupled and the cross-sectional area is halved. The corresponding filling time is t2. The ratio t2/t1 is
t1=Volume of cavityFlow rate=VA×√2gh
For t2
h2=4h,A2=A2
t2=VA2×√2×g×4h
t2=VA√2gh=t1
t1t2=1