A PERT network consists of 5 activities with the following duration.
Activity | Predecessor | Optimistic time (days) |
Most likely time (days) |
Pessimistic time (days) |
P | - | 2 | 4 | 6 |
Q | P | 4 | 5 | 12 |
R | P | 5 | 8 | 11 |
S | Q | 2 | 5 | 8 |
T | R | 4 | 6 | 14 |
VCP=(6−26)2+(11−56)2+(14−46)2
=136(16+36+100)=4.22