wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

A PERT network consists of 5 activities with the following duration.

Activity Predecessor Optimistic
time (days)
Most
likely
time
(days)
Pessimistic
time (days)
P - 2 4 6
Q P 4 5 12
R P 5 8 11
S Q 2 5 8
T R 4 6 14

The variance of the critical path is _______

A
2.84
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
3.66
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
5
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
4.22
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 4.22

VCP=(626)2+(1156)2+(1446)2

=136(16+36+100)=4.22


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Weighted Average
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon