Question

A PERT network has 9 activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is

A
27
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
9
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
3
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
81
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 9
In CPM,

σ=sum of variance along critical path

σ=σ2+σ2+.....+σ2

σ=9σ2=9×9=9