Question

A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviation 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is

A
0.50
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
0.66
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
0.95
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
0.84
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 0.84
Estimated completion time Tθ=3+8+6=17

Standard deviation, σ=σ2=12+22+22=3

z=TTeσ=20173=1

Probability= 0.84

flag
Suggest Corrections
thumbs-up
19
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Mean Deviation about Mean for Discrete Frequency Distributions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon