Question
A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviation 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is
A
0.50
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
0.66
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
0.95
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
0.84
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution
The correct option is D 0.84 Estimated completion time Tθ=3+8+6=17