A pond is dug in 4 days and requires 12 men. If there is an inverse relationship between the number of men required to dig a well and the number of days, calculate the number of men required to dig the well in 1 day.
A
12
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
48
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
36
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
49
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B 48 Let the number of days requires to dig a pond be D and the number of men required to dig the pond be M.
Given that D∝1M ⇒D=kM ; where k is a constant
According to the question,
A pond is dug in 4 days which requires 12 men
i.e. D=4,M=12
We know, D=kM⇒4=k12⇒k=48
Now, if the pond has to be dug in 1 day,
i.e. D=1,M=?
We know, D=kM ⇒1=48M(∵k=48) ⇒M=48
Hence, 48 men are required to dig the pond in 1 day.